Cable selection algorithm · U_m > 36 kV
HV cable system selection algorithm
Above 36 kV a cable is not selected on its own — the cable, its accessories and its bonding are rated and qualified as one system. This is that sequence: which standard applies, the bonding decided before the rating, the full thermal model, the screen fault current, and the test evidence that has to exist behind it.
Above 36 kV the object being selected is a cable system, not a cable: the cable, the joints, the terminations and the bonding are qualified and rated together. IEC 60840 applies above 30 kV (U_m 36 kV) up to 150 kV (U_m 170 kV); IEC 62067 applies above that up to 500 kV (U_m 550 kV), and adds a prequalification test of the complete system.
Two things reorder the algorithm compared with MV. The bonding scheme has to be decided before the rating is calculated, because solid, single-point and cross-bonding give completely different sheath loss factors (IEC 60287-1-1, 2.3). And the thermal environment becomes an input that has to be surveyed: dielectric loss is no longer negligible (2.2), mutual heating between circuits dominates T4, and the risk of the soil drying out around the cable is a design case, not a footnote (IEC 60183, 4.3.2 d).
The algorithm
The steps in words
| # | Check or action | Criterion | Reference |
|---|---|---|---|
| 1 | Collect the system, route and thermal data | At HV the thermal survey of the route is part of the input data, not an assumption. | IEC 60183, 4.2 and 4.3.1 to 4.3.4 |
| 2 | Place the circuit in its voltage standard | The applicable test standard, U_m and U_p — settled before any conductor is sized. | IEC 60840, Clause 1; IEC 62067, Clause 1; IEC 60183, 5.3 and 5.4, Table 1 |
| 3 | Choose the cable system design | Screen able to carry the full fault current, and a water barrier wherever the route can be wet. | IEC 60840, 4.2 to 4.4 and Clause 5, Tables 1 and 2; IEC 62067, 4.2 to 4.4 |
| 4 | Decide the bonding scheme first | Bonding scheme, plus the SVLs and earth continuity conductor it implies. | IEC 60183, 4.2 f); IEC 60287-1-1, 2.3 |
| 5 | Take a trial conductor size and formation | Size, formation, spacing and depth as one trial arrangement. | IEC 60183, Clause 6 a) to e); IEC 60228 |
| 6 | Calculate the rating properly | Conductor temperature at the design load, from the full IEC 60287 model for the real trench section. | IEC 60287-1-1, 1.4.1.1, 2.1 to 2.4; IEC 60287-2-1, 4.1.2 to 4.2.7; IEC 60287-3-1 |
| 7 | Conductor temperature within the Table 1 limit | engineered thermal backfill, wider spacing and deeper burial pull in different directions — depth raises T4; forced cooling is a design commitment, not a fix | IEC 60840 or IEC 62067, Table 1; IEC 61936-1, 6.2.9.1 |
| 8 | Route safe against soil drying out | a trench that dries out around the cable moves the soil resistivity far from the assumed value; a rating built on an assumed 1,0 to 1,5 K·m/W and no survey is the classic HV design failure | IEC 60183, 4.3.2 d); IEC 60287-3-1 for soil data |
| 9 | Conductor withstands the short-circuit | I = ε·I_AD; above 36 kV take the permitted final temperature from the manufacturer's qualified design — IEC 60986 covers only 6 kV to 30 kV | IEC 60949, Clauses 2 and 3 |
| 10 | Screen withstands the earth-fault current | with single-point bonding the whole earth-fault current has one return path; the screen temperature limit is set by the material in contact with it | IEC 60949, Clause 6; IEC 60840, 4.3, note |
| 11 | Check the thermo-mechanical and pulling design | Expansion, pulling force, short-circuit force and crossings all resolved on the drawings. | IEC 61936-1, 6.2.9.2 and 6.2.9.5; IEC 60183, 7.1 |
| 12 | Specify and qualify the accessories | Cable system type-tested and, above U_m 170 kV, prequalified — with the range of approval covering this design. | IEC 60840 and IEC 62067, type approval and Clause 13 prequalification; IEC 60183, 7.2 and 7.3; IEC TS 60815-1; IEC 62271-209 |
| 13 | Decide on monitoring | Monitoring scope agreed, or a written decision not to monitor. | IEC 60183, Annex A |
What actually governs the size
Running the algorithm is mechanical. Knowing which check will bind before you start is what makes it quick — and what tells you whether a schedule someone else produced was ever checked at all.
| Case | What binds |
|---|---|
| Almost every buried link | T4 and the soil. Mutual heating, depth and thermal resistivity decide the rating; the conductor size is often the smallest of the levers available. |
| Single-core circuits, which is all of them | The bonding scheme, decided first. It sets the sheath loss, the sheath voltage, whether SVLs and an earth continuity conductor are needed, and the length of an electrical section. |
| Circuits at 132 kV and above | Dielectric loss. W_d = ω·C·U₀²·tan δ is a fixed loss that exists at no load and cannot be designed away — Table 3 of IEC 60287-1-1 gives the U₀ above which it must be counted. |
| Earth faults | The screen. Under single-point bonding the whole earth-fault current has one return path, and above 36 kV the permitted screen temperature comes from the manufacturer's qualified design — IEC 60986 stops at 30 kV. |
| The procurement stage | The evidence. The type-test range of approval must actually cover the cross-section and construction offered, and above U_m 170 kV a prequalification test of the complete system applies (IEC 62067, Clause 13). |
Standards this algorithm is built from
| Standard | What it supplies here |
|---|---|
| IEC 60840:2011 | Cable systems above 30 kV (U_m 36 kV) up to 150 kV (U_m 170 kV) — test methods and requirements |
| IEC 62067:2011 | Cable systems above 150 kV (U_m 170 kV) up to 500 kV (U_m 550 kV), with prequalification |
| IEC 60183:2015 | Guidance for the selection of high-voltage a.c. cable systems |
| IEC 60287-1-1, -2-1, -3-1 | Rating equations and losses, thermal resistances, soil and ambient data |
| IEC 60853-2 and -3 | Cyclic and emergency ratings |
| IEC 60071-1:2011 | Insulation coordination — the impulse withstand level U_p |
| IEC 60949:1988+A1:2008 | Thermally permissible short-circuit currents |
| IEC 61936-1:2010+A1:2014 | Installation requirements for cables in power installations above 1 kV |
The clause and formula numbers above were read from the standards themselves. What is not reproduced anywhere on this site is the text of a standard: if you calculate for a living, buy the document from IEC. How each engine here is checked against the standards' own published values is on the validation page.